WINDY HILL ROAD
Limits: IH 35 Frontage Road to Purple Martin Avenue
Project Updates
Summer 2026
Construction continues with Phase 1B excavation along the roadway realignment footprint, subgrade grading, fence gate installation at the Dacy property easement, and installation of stormwater trunklines, manholes, and inlets.
Upcoming work includes widening the existing bridge-class culvert, installation of utility infrastructure, continued water and sewer improvements, and utility relocation.
Overview
The project will expand the roadway to four lanes, improve intersections, extend the culvert at the Richmond Branch low water crossing, and add modern drainage facilities. Once complete, this investment will provide a safer, more efficient roadway that supports Kyle’s continued growth.
2022 Road Bond Update
Per City Council direction on July 7, 2026, we are conducting updated traffic studies to reevaluate intersections throughout the City of Kyle. A recommendation will be provided once updated data has been collected and analyzed. Pedestrian facility is also being evaluated. Due to these ongoing evaluations, current plans are subject to change.
-
Length: Approximately 0.6 miles
Location: From IH 35 Northbound Frontage Road to Purple Martin Avenue
-
Widening the roadway to add a center turn lane, shoulders and space for mailboxes
Constructing intersection improvements at Cherrywood, Indian Paintbrush Drive, and Purple Martin Avenue
Constructing culvert upgrades and drainage improvements
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost= $15.1 M
-
Construction: Spring 2026 -Summer 2027
Schedule and Project Status
Project Resources
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Click on the title below to view:
Frequently Asked Questions
-
In November 2022, Kyle voters approved Proposition A, authorizing $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city. Proposition A in the 2022 Road Bond Program includes eight roadway projects totaling 10.3 miles. These projects support current and long-term growth in the City of Kyle by increasing mobility, reducing congestion, enhancing safety, and strengthening community connectivity for drivers and pedestrians. More information is available at KyleRoadBonds.com.
-
The Windy Hill Road Improvement Project will reconstruct and widen the existing roadway while addressing drainage and flooding concerns through culvert and stormwater upgrades. The project also includes intersection improvements at Cherrywood to enhance safety and traffic operations. Once complete, these enhancements will improve traffic flow, increase safety, and provide long-term reliability for this important east-west connection.
-
The project extends approximately 0.6 miles from IH 35 Northbound Frontage Road to Purple Martin Avenue. This section of Windy Hill Road serves as an important east-west connector between residential neighborhoods and IH 35.
-
The planned improvements include:
Widening the roadway for two travel lanes in each direction, along with dedicated center turn lane to accommodate higher traffic volume
New pedestrian facilities to improve safety and mobility for all users
Construction of intersection improvements at Cherrywood to enhance safety and traffic operations
Improved drainage infrastructure through construction of storm sewer and culvert extensions helping manage stormwater more efficiently and protect the roadway
-
Windy Hill Road currently experiences capacity limitations, safety challenges, and drainage issues due to increased traffic and aging infrastructure. These improvements will enhance safety, improve traffic flow, and address flood-prone areas to ensure the roadway meets both current and future transportation needs.
-
The Windy Hill Road Improvement Project is funded through the City of Kyle's 2022 Road Bond Program (Proposition A), approved by Kyle voters in November 2022. Proposition A authorized $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city, with eight roadway projects totaling 10.3 miles. The estimated construction cost for the Windy Hill Road project is $15.1 million. Cost includes project design, right-of-way acquisition, utility coordination, and construction. More information about the Road Bond Program is available at KyleRoadBonds.com.
-
Preliminary analysis for the Windy Hill Road Improvement Project began in 2024. Design and environmental analysis are complete, and construction is currently underway. Construction is anticipated to be complete in Summer 2027.
-
Residents and drivers along Windy Hill Road can expect temporary lane restrictions, construction equipment in the roadway, and some delays during active work hours. Driveway and property access will be maintained throughout construction. The reconstruction of the Richmond Branch low water crossing may require temporary restrictions to that segment during key phases of work. All impacts will be communicated in advance through posted signage and updates at KyleRoadBonds.com. Once complete, the improved low water crossing will significantly reduce flooding that has historically caused road closures during heavy rain events, providing a more reliable route for residents year-round.
-
Before construction begins, "Coming Soon" signs will be placed along the roadway to notify the community of upcoming work. The project team will continue coordinating with utility providers and finalizing construction schedules to minimize disruptions. Once construction begins, the City's Road Bond Website will share regular updates on traffic impacts, detours, and progress milestones. Residents are encouraged to join the Road Bond Program Newsletter for digital updates to stay informed and prepared throughout each stage of the project.
-
If you have any questions or want to learn more, visit KyleRoadBonds.com/contact or call (512) 200-4963.
For road maintenance requests, contact Kyle 3-1-1 by calling 3-1-1 or visiting Kyle311.com.
In accordance with Title VI of the Civil Rights Act of 1964 and related statutes, it is the policy of the City of Kyle to ensure that no person shall be excluded from participation in, denied the benefits of, or otherwise subjected to discrimination under any programs or activities on the grounds of race, color, national origin, sex, age, or disability.