KYLE PARKWAY - LEHMAN ROAD
Limits: Lehman Road northeast from Bunton Creek Road to Dacy Lane, and extension of Kyle Parkway to connect to the new segment of Lehman
Project Updates
Summer 2026
Design remains at 95% completion. Final plans were partially submitted on June 30, 2026. Bid advertising is anticipated for late Summer 2026 but may be placed on hold pending the City Council's intersection analysis. AT&T utility relocation is complete, and right-of-way clearance is anticipated to be completed at the end of Summer 2026.
Overview
This project will improve mobility and reduce congestion in Northeast Kyle by extending Lehman Road northeast from Bunton Creek Road to Dacy Lane as a four-lane roadway and extending Kyle Parkway to connect with the new segment.
2022 Road Bond Update
Per City Council direction on July 7, 2026, we are conducting updated traffic studies to reevaluate intersections throughout the City of Kyle. A recommendation will be provided once updated data has been collected and analyzed. Pedestrian facility is also being evaluated. Due to these ongoing evaluations, current plans are subject to change.
-
Length: Approximately 1.3 miles
Location:
Lehman Road - Dacy Lane to Bunton Creek Road
Kyle Parkway- Dacy Lane to new Lehman Road segment
-
Improve mobility and reduce congestion in Northeast Kyle by extending Lehman Road northeast from Bunton Creek Road to Dacy Lane as a 4-lane roadway
Extend Kyle Parkway to connect with the new segment
New pedestrian routes to improve safety and mobility for all users
Construct intersection improvements at the following locations to enhance safety and traffic operations:
Kyle Parkway & Dacy Lane
Kyle Parkway & Lehman Road
Lehman Road & Bunton Creek Road
Lehman Road & Dacy Lane
Improve drainage infrastructure through culvert upgrades and new curb and gutter construction, helping reduce flooding and protect the roadway
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $42.5 M
-
Requests for Construction Proposals: Early 2026, following design approval
Construction: to begin Spring 2026 and complete in Fall 2027
Schedule and Project Status
Project Resources
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Click on the title below to view:
Kyle Parkway to Lehman Road Preliminary Engineering Report (PER)
Frequently Asked Questions
-
In November 2022, Kyle voters approved Proposition A, authorizing $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city. Proposition A in the 2022 Road Bond Program includes eight roadway projects totaling 10.3 miles. These projects support current and long-term growth in the City of Kyle by increasing mobility, reducing congestion, enhancing safety, and strengthening community connectivity for drivers and pedestrians. More information is available at KyleRoadBonds.com.
-
The Kyle Parkway and Lehman Road Extension Project is part of the City of Kyle's 2022 Road Bond Plan to address future transportation needs. As traffic demands continue to increase in Kyle, the City is dedicated to providing safe travel, reducing time spent in traffic, and improving mobility for drivers, pedestrians, and bicyclists. The project will extend Lehman Road northeast from Bunton Creek Road to Dacy Lane as a four-lane minor arterial roadway and extend Kyle Parkway to connect with the new segment of Lehman Road. The total length of the new roadway will cover approximately 1.3 miles. Improvements will include four two-lane intersection improvements at Kyle Parkway and Dacy Lane, Kyle Parkway and Lehman Road, Lehman Road and Bunton Creek Road, and Lehman Road and Dacy Lane.
-
The project extends approximately 1.3 miles from Bunton Creek Road to Dacy Lane. The project will extend Lehman Road northeast as a four-lane roadway and extend Kyle Parkway to connect with this new segment of Lehman Road.
-
Improve mobility and reduce congestion in Northeast Kyle by extending Lehman Road northeast from Bunton Creek Road to Dacy Lane as a 4-lane roadway
Extend Kyle Parkway to connect with the new segment
New pedestrian routes to improve safety and mobility for all users
Construct intersection improvements at the following locations to enhance safety and traffic operations:
Kyle Parkway & Dacy Lane
Kyle Parkway & Lehman Road
Lehman Road & Bunton Creek Road
Lehman Road & Dacy Lane
Improve drainage infrastructure through culvert upgrades and new curb and gutter construction, helping reduce flooding and protect the roadway
-
The City of Kyle has experienced unprecedented growth over the past decade, with new residential communities and commercial businesses expanding rapidly on the east side of town. The current roadway network cannot accommodate the growing volume of traffic from drivers who rely on it as a critical east-west connection. The project will address this demand by constructing new roadway capacity, intersection improvements to address traffic flow and safety, drainage improvements, and new pedestrian routes to improve safety and mobility for all users, as well as trees and landscaping.
-
The Kyle Parkway and Lehman Road Extension Project is funded through the City of Kyle's 2022 Road Bond Program (Proposition A), approved by Kyle voters in November 2022. Proposition A authorized $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city, with eight roadway projects totaling 10.3 miles. The estimated project cost is approximately $42.5 million. Cost includes project design, right-of-way acquisition, utility coordination, and construction. More information about the Road Bond Program is available at KyleRoadBonds.com.
-
Preliminary analysis began in 2024. Design is nearing completion, and the project is preparing to move into the contractor selection phase, during which qualified contractors will submit construction proposals for City review. Following contractor selection and City approval, construction is anticipated to begin in Fall 2026 and be completed in Winter 2027.
-
Because this project involves new roadway construction, right-of-way acquisition is required in some areas. The City works closely with property owners along the alignment to keep them informed of the project's status. Where right-of-way is needed, the City will work with property owners to purchase the land through a fair and transparent process, including independent appraisals to determine fair market value. Property owners along the alignment will be contacted directly by the project team. For questions about right-of-way, call (512) 200-4963.
-
The City's Road Bond Website will share regular updates on construction timelines, traffic impacts, detours, and progress milestones. Residents are encouraged to join the Road Bond Program Newsletter for digital updates to stay informed and prepared throughout each stage of the project.
-
If you have any questions or want to learn more, visit KyleRoadBonds.com/contact or call (512) 200-4963.
For road maintenance requests, contact Kyle 3-1-1 by calling 3-1-1 or visiting Kyle311.com.
In accordance with Title VI of the Civil Rights Act of 1964 and related statutes, it is the policy of the City of Kyle to ensure that no person shall be excluded from participation in, denied the benefits of, or otherwise subjected to discrimination under any programs or activities on the grounds of race, color, national origin, sex, age, or disability.