Committed to supporting safer, more connected roadways in Kyle.
The City of Kyle is kicking off 8 major roadway projects across Kyle, adding 10.3 miles of new and improved roads.
These upgrades will:
Make travel smoother and safer for drivers, bikers, and pedestrians
Strengthen connections between Kyle’s east and west sides
Expand the Vybe Trail System to give our community more ways to stay active and connected
News & Events
-
The City of Kyle invites residents to a community information session on Wednesday, February 25, from 6:00–8:00 p.m. at the Kyle Public Library.
The event will provide a Road Bond update and brief highlights of city projects supporting Kyle’s continued growth. Light refreshments will be provided.
-
This spring, the City will celebrate progress on several Road Bond projects that are moving to the construction phase. Details on groundbreaking dates and locations will be shared soon.
-
Here's the road bond projects next in line for contractor bidding and then construction:
Kyle Parkway - Lehman Road Extension
Old Stagecoach Road
Old Stagecoach North
Center Street (East Segment)
The contractor bidding phase is when the finalized project plans are advertised and qualified contractors submit competitive bids to construct the improvements. After reviewing the bids for responsiveness, cost, and experience, the City selects a contractor and prepares to move into construction
OUR PROJECTS
-

BEBEE ROAD
WEST SEGMENT: CONSTRUCTION SUMMER 2025 - SUMMER 2027
EAST SEGMENT: CONSTRUCTION FALL 2027- FALL 2029
-

BUNTON CREEK ROAD
BID ADVERTISEMENT WINTER 2025
CONSTRUCTION SUMMER 2026 - SUMMER 2028
-

CENTER STREET
FINAL DESIGN
CONSTRUCTION FALL 2026 - FALL 2027
-

KOHLERS TO SETON
IH-35 UNDERPASS: EARLY DESIGN. CONSTRUCTION FALL 2027 - FALL 2029
TO SETON: CONSTRUCTION SUMMER 2025 - SUMMER 2027
-

KYLE PARKWAY - LEHMAN EXT.
FINAL DESIGN
CONSTRUCTION SPRING 2026 - FALL 2027
-

MARKETPLACE AVENUE
CONSTRUCTION
COMPLETED SUMMER 2025
-

OLD STAGECOACH ROAD
OSC NORTH: CONSTRUCTION SPRING 2026 - SUMMER 2027
OSC: CONSTRUCTION SPRING 2026 - SUMMER 2027
CENTER STREET (WEST): BID ADVERTISEMENT WINTER 2025. CONSTRUCTION SPRING 2026 - SUMMER 2027
-

WINDY HILL ROAD
BID ADVERTISEMENT WINTER 2025
CONSTRUCTION SPRING 2026 - SUMMER 2027