Keep Kyle Moving

News & Events

  • The City of Kyle will be hosting a community open house on July 29th at Lehman High School from 6:30 - 8:00 PM.

    This event will cover both road bond and general city project updates, including a Utility District update. City staff, project engineers, and city leaders will be available to answer questions and discuss how these projects are improving mobility and infrastructure across Kyle.

  • Here's the road bond projects next in line for contractor bidding and then construction:

    • Kyle Parkway - Lehman Road Extension

    • Old Stagecoach Road

    • Old Stagecoach North

    • Center Street (East Segment)

    The contractor bidding phase is when the finalized project plans are advertised and qualified contractors submit competitive bids to construct the improvements. After reviewing the bids for responsiveness, cost, and experience, the City selects a contractor and prepares to move into construction

OUR PROJECTS

  • BEBEE ROAD

    WEST SEGMENT: CONSTRUCTION SUMMER 2025 - SUMMER 2027

    EAST SEGMENT: CONSTRUCTION FALL 2027- FALL 2029

  • BUNTON CREEK ROAD

    BID ADVERTISEMENT WINTER 2025

    CONSTRUCTION SUMMER 2026 - SUMMER 2028

  • CENTER STREET

    FINAL DESIGN

    CONSTRUCTION FALL 2026 - FALL 2027

  • KOHLERS TO SETON

    IH-35 UNDERPASS: EARLY DESIGN. CONSTRUCTION FALL 2027 - FALL 2029

    TO SETON: CONSTRUCTION SUMMER 2025 - SUMMER 2027

  • KYLE PARKWAY - LEHMAN EXT.

    FINAL DESIGN

    CONSTRUCTION SPRING 2026 - FALL 2027

  • MARKETPLACE AVENUE

    CONSTRUCTION

    COMPLETED SUMMER 2025

  • OLD STAGECOACH ROAD

    OSC NORTH: CONSTRUCTION SPRING 2026 - SUMMER 2027

    OSC: CONSTRUCTION SPRING 2026 - SUMMER 2027

    CENTER STREET (WEST): BID ADVERTISEMENT WINTER 2025. CONSTRUCTION SPRING 2026 - SUMMER 2027

  • WINDY HILL ROAD

    BID ADVERTISEMENT WINTER 2025

    CONSTRUCTION SPRING 2026 - SUMMER 2027

The City of Kyle has officially launched 8 major roadway projects across the community, delivering a total of 10.3 miles of new and improved roadways

These upgrades will:

  • Make travel smoother and safer for drivers, bikers, and pedestrians

  • Strengthen connections between Kyle’s east and west sides

  • Expand the Vybe Trail System to give our community more ways to stay active and connected