Keep Kyle Moving

News & Events

OUR PROJECTS

  • BEBEE ROAD

    WEST SEGMENT: CONSTRUCTION SUMMER 2025 - SUMMER 2027

    EAST SEGMENT: CONSTRUCTION FALL 2027- FALL 2029

  • BUNTON CREEK ROAD

    CONSTRUCTION SUMMER 2026 - SUMMER 2028

  • CENTER STREET

    FINAL DESIGN

    CONSTRUCTION FALL 2026 - FALL 2027

  • KOHLERS TO SETON

    IH-35 UNDERPASS: EARLY DESIGN. CONSTRUCTION FALL 2027 - FALL 2029

    TO SETON: CONSTRUCTION SUMMER 2025 - SUMMER 2027

  • KYLE PARKWAY - LEHMAN EXT.

    FINAL DESIGN

    CONSTRUCTION SUMMER 2026 - FALL 2027

  • MARKETPLACE AVENUE

    COMPLETED SUMMER 2025

  • OLD STAGECOACH ROAD

    OSC NORTH: CONSTRUCTION FALL 2026 - SUMMER 2027

    OSC: CONSTRUCTION FALL 2026 - WINTER 2028

    CENTER STREET (OFF-SYSTEM): CONSTRUCTION SUMMER 2026 - SUMMER 2028

  • WINDY HILL ROAD

    CONSTRUCTION SPRING 2026 - SUMMER 2027

The City of Kyle has officially launched 8 major roadway projects across the community, delivering a total of 10.3 miles of new and improved roadways

These upgrades will:

  • Make travel smoother and safer for drivers, bikers, and pedestrians

  • Strengthen connections between Kyle’s east and west sides

  • Expand the Vybe Trail System to give our community more ways to stay active and connected