CENTER STREET
Off TxDOT System Limits: From Old Stagecoach Road to Veterans Drive
On (TxDOT) System Limits: From Veterans Drive to Main Street
Center Street projects connect with the Old Stagecoach Road projects. Information of those projects can be found here.
Project Updates
Updated Weekly
Center Street (On TxDOT System)- Final Design
The project has been on hold under City Council direction since October 5, 2026. City Council previously directed PEC utilities to be placed underground and confirmed the Vybe Trail width. The updated design schedule has not yet been determined.
Center Street (Off TxDOT System) - Construction
The project is moving forward following City Council direction to proceed with the original project scope, including a roundabout at Center Street and Old Stagecoach Road, underground utilities, and a 12-foot-wide hike-and-bike trail. A coordination meeting was held with the contractor to discuss restarting construction, and an updated construction schedule is being developed to establish a new start date and implement a phased construction approach.
Preparatory work completed to date includes installation of project signage, initial traffic control measures, and utility potholing. Upcoming work includes installation of right-of-way fencing, stormwater protection measures, pond construction, storm drainage improvements, reinforced concrete pipe installation, inlets, manholes, and culvert replacement.
The anticipated roadway opening remains Fall 2028.
Overview
On Center Street the existing three-lane section will be improved by widening the center lane to enhance operations.
2022 Road Bond Update
Per City Council direction on July 7, 2026, updated traffic studies are underway to reevaluate intersections throughout the City of Kyle. Pedestrian facilities are also being evaluated. Council has made decisions on six of the 12 intersections under review, with recommendations for the remaining intersections pending Council approval. Due to these ongoing evaluations, current plans and project timelines are subject to change.
-
Center Street (On-System)
Length: Approximately 0.4 miles.
Location: From Veterans Drive to Main Street
Center Street (Off-System)
Length: 0.62 miles
Location: Old Stagecoach Road to Veterans Drive (RM 150)
-
Expand Center Street from two lanes to three lanes to increase capacity
Improve road and intersection infrastructure to enhance safety and reduce congestion
Enhance drainage and supporting utilities along the corridor
Improve sidewalks and pedestrian crossings for better downtown accessibility
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $10.2 M
-
Design Phase: Currently in progress
Request for Construction Proposals: To be scheduled following right of way and utility coordination
Construction: Summer 2027 - Winter 2028
Project Resources
-
Click on the title below to view each item.
Center Street (On-System) detailed project schematic
Center Street (Off TxDOT System) detailed project schematic
-
Click on the title below to view each item.
Center Street (On-System) Locator map
-
Frequently Asked Questions
-
In November 2022, Kyle voters approved Proposition A, authorizing $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city. Proposition A in the 2022 Road Bond Program includes eight roadway projects totaling 10.3 miles. These projects support current and long-term growth in the City of Kyle by increasing mobility, reducing congestion, enhancing safety, and strengthening community connectivity for drivers and pedestrians. More information is available at KyleRoadBonds.com.
-
The Center Street Improvement Project is a planned roadway expansion and infrastructure upgrade in downtown Kyle. The project will expand Center Street from Veterans Drive to Main Street. These improvements aim to reduce congestion, enhance safety, and improve mobility for drivers, pedestrians, and cyclists traveling through Kyle's downtown core.
-
The project takes place on approximately 1.02 miles of Center Street from Old Stagecoach Road to Main Street in downtown Kyle. This location was selected for improvements to enhance connectivity and accessibility throughout downtown Kyle and adjacent neighborhoods.
-
Center Street will be widened to provide one travel lane in each direction, along with a dedicated center turn lane to improve traffic flow and reduce congestion. The intersection at Veterans Drive (RM 150) will be improved to enhance safety and traffic operations. The project will also include drainage infrastructure improvements, and new pedestrian routes and crossing enhancements to improve safety and mobility for all users.
-
Downtown Kyle is experiencing increased traffic congestion as more residents, visitors, and businesses travel along Center Street to access the heart of the community. The existing roadway has limited capacity, which contributes to delays and safety challenges. Expanding and improving Center Street will help traffic move more efficiently and safely between neighborhoods, downtown destinations, and other key city corridors.
-
The Center Street Improvement Project is funded through the City of Kyle's 2022 Road Bond Program (Proposition A), approved by Kyle voters in November 2022. Proposition A authorized $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city, with eight roadway projects totaling 10.3 miles. Approximately $10.2 million has been allocated for the construction of this project. Cost includes project design, right-of-way acquisition, utility coordination, and construction. More information about the Road Bond Program is available at KyleRoadBonds.com.
-
The design phase began in 2024. Because this project is located on a state highway, it requires coordination and approval from the Texas Department of Transportation (TxDOT) before moving forward. Once design is complete and approvals are in place, the project will move into the contractor selection phase, during which qualified contractors will submit construction proposals for City review. Construction is anticipated from Summer 2027 through Winter 2028.
-
Because this project takes place in downtown Kyle, impacts will be felt by residents, businesses, and visitors who travel through the area daily. Lane reductions along Center Street between Veterans Drive and Main Street will be in effect during active construction phases. The City will work closely with downtown businesses to maintain access and visibility throughout the project. Pedestrian detour routes will be clearly marked when sidewalks are under construction. Updates on traffic impacts and detours will be posted at KyleRoadBonds.com and communicated through the Road Bond Newsletter.
-
The City's Road Bond Website will share regular updates on construction timelines, traffic impacts, detours, and progress milestones. Residents are encouraged to join the Road Bond Program Newsletter for digital updates to stay informed and prepared throughout each stage of the project.
-
If you have any questions or want to learn more, visit KyleRoadBonds.com/contact or call (512) 200-4963.
For road maintenance requests, contact Kyle 3-1-1 by calling 3-1-1 or visiting Kyle311.com.
In accordance with Title VI of the Civil Rights Act of 1964 and related statutes, it is the policy of the City of Kyle to ensure that no person shall be excluded from participation in, denied the benefits of, or otherwise subjected to discrimination under any programs or activities on the grounds of race, color, national origin, sex, age, or disability.