OLD STAGECOACH ROAD - CENTER STREET
Limits on the 3 segments that will be constructed independently to accelerate delivery:
Old Stagecoach Road North Limits: From Six Creeks Boulevard to Veterans Drive.
Old Stagecoach Road Limits: From Six Creeks Boulevard to Center Street.
Center Street (Off-System) Limits: From Old Stagecoach Road to Veterans Drive.
Center Street (Off-System) Construction Notice
Starting July 13, 2026, and continuing through summer 2027, construction crews will be visible at the 5-way traffic stop at West Center Street and Old Stagecoach Road.
Work includes potholing and building drainage improvements as part of the Center Street (Off-System) 2022 Road Bond Project. This work is independent and unaffected by ongoing intersection reevaluations.
All lanes will stay open, and traffic will not be impacted. Construction barrels along the edge of the road will mark relevant work zones.
We ask that drivers increase their awareness and slow down in work zones. Construction zones protect workers, drivers, cyclists, and pedestrians.
Project Updates
Summer 2026
Old Stagecoach Road North - Final Design
The final design plans (100% PS&E) are under review. In addition, all right-of-way is expected to be complete by Summer 2026.
Old Stagecoach Road - Final Design
The final design was submitted on June 24, 2026. Four parcels remain to be acquired. Utility relocation is expected to begin in Summer 2026.
Center Street (Off TxDOT System) - Construction
Construction is underway following the Notice to Proceed issued on June 22, 2026.
Ongoing activities include stormwater pollution prevention measures for Phase 1 Stage A and potholing to identify existing utilities before construction progresses.
Upcoming work includes installation of property fencing within the new right-of-way, pond construction, storm drainage infrastructure, reinforced concrete pipe, inlets, manholes, culvert replacement, and a new detour that will allow work to continue in other project areas while supporting ongoing roundabout evaluations.
Overview
The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.
2022 Road Bond Update
Per City Council direction on July 7, 2026, we are conducting updated traffic studies to reevaluate intersections throughout the City of Kyle. A recommendation will be provided once updated data has been collected and analyzed. Pedestrian facility is also being evaluated. Due to these ongoing evaluations, current plans are subject to change.
-
Old Stagecoach Road North
Length: 0.50 miles
Location: Six Creeks Boulevard to Veterans Drive (RM 150)
Old Stagecoach Road
Length: 1.02 miles
Location: Center Street to Six Creeks Boulevard
Center Street (West Segment)
Length: 0.62 miles
Location: Old Stagecoach Road to Veterans Drive (RM 150)
-
Old Stagecoach Road North
4-lane reconstruction and widening
Old Stagecoach Road
Expand roadway to one lane in each direction with a middle left turn lane
Center Street (West Segment)
Expand roadway to one lane in each direction with a middle left turn lane
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $41.2 M
-
Kyle City Council opted to bid all three segments independently to accelerate delivery.
Old Stagecoach Road North
Construction: Fall 2026 - Fall 2027
Old Stagecoach Road
Construction: Fall 2026 - Fall 2027
Center Street (Off-system)
Construction: Summer 2026 - Fall 2028
Schedule and Project Status
Project Resources
-
Click on the title below to view each segment.
-
Click on the title below to view each item.
-
Looking for detailed information about the Old Stagecoach Heritage Live Oak?
Visit our dedicated Old Stagecoach Heritage Live Oak Tree page. -
Click on the title below to view:
Old Stagecoach Road & Center Street (off-system) Preliminary Engineering Report (PER)
-
Click on the title to view each item:
Frequently Asked Questions
-
In November 2022, Kyle voters approved Proposition A, authorizing $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city. Proposition A in the 2022 Road Bond Program includes eight roadway projects totaling 10.3 miles. These projects support current and long-term growth in the City of Kyle by increasing mobility, reducing congestion, enhancing safety, and strengthening community connectivity for drivers and pedestrians. More information is available at KyleRoadBonds.com.
-
The Old Stagecoach Road and Center Street Improvement Project will improve approximately 2.2 miles of Old Stagecoach Road North, Old Stagecoach Road, and a portion of Center Street to reduce traffic congestion, enhance safety, and improve overall traffic flow. Old Stagecoach Road North will be expanded to a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. Improvements on Center Street include widening the existing center lane to enhance traffic operations. Two new intersection improvements will be constructed at the intersection of Six Creeks Boulevard and Old Stagecoach Road North, and at the intersection of Center Street and Old Stagecoach Road.
-
To accelerate delivery, the project will be constructed in three independent segments:
Old Stagecoach Road North: approximately 0.50 miles from Six Creeks Boulevard to Veterans Drive
Old Stagecoach Road: approximately 1.02 miles from Center Street to Six Creeks Boulevard
Center Street (Off-System): approximately 0.62 miles from Veterans Drive to Old Stagecoach Road
Together, these segments improve a key transportation corridor that connects nearby residential neighborhoods to major roadways, enhancing safety, mobility, and overall traffic flow.
-
The planned improvements include:
Reconstructing and widening the roadway to improve traffic flow and accommodate future growth
Constructing intersection improvements at Six Creeks Boulevard and Old Stagecoach Road, and Center Street and Old Stagecoach Road to enhance safety and traffic operations
New pedestrian routes to improve safety and mobility for all users
Culvert upgrades and new curb and gutter construction, helping to reduce flooding and protect the roadway
-
The Old Stagecoach Road and Center Street corridor currently faces traffic congestion, safety concerns, and drainage challenges due to increased traffic volumes and aging infrastructure. These improvements are needed to enhance safety, improve traffic flow, and address flood-prone areas, ensuring the roadway can meet both current and future transportation needs for drivers, pedestrians, and cyclists.
-
The Old Stagecoach Road and Center Street Improvement Project is funded through the City of Kyle's 2022 Road Bond Program (Proposition A), approved by Kyle voters in November 2022. Proposition A authorized $294.4 million in funding to construct, expand, and upgrade roadways and infrastructure across the city, with eight roadway projects totaling 10.3 miles. The estimated construction cost for the Old Stagecoach Road and Center Street project is $41.2 million. Cost includes project design, right-of-way acquisition, utility coordination, and construction. More information about the Road Bond Program is available at KyleRoadBonds.com.
-
Preliminary analysis began in 2023. Kyle City Council opted to move all three segments into design and construction independently to accelerate delivery. Segment timelines are as follows:
Old Stagecoach Road North: Design is ongoing and construction is anticipated Fall 2026 through Fall 2027.
Old Stagecoach Road: Design is complete, and all right-of-way has been secured, pending four parcel dedications. Construction is anticipated for Fall 2026 through Fall 2027.
Center Street (Off-System): A contractor has been selected, and the project is advancing toward construction. Construction is anticipated Summer 2026 through Summer 2028.
-
Because this project covers 2.2 miles across three segments, impacts will vary by location and phase of construction. Residents and drivers can expect lane reductions, detour routes at key intersections, and construction equipment along the corridor for an extended period. During roundabout construction at Six Creeks Boulevard and at Center Street, temporary traffic control measures including flagging operations will be in place. Property and driveway access will be maintained throughout construction. The City will communicate segment-specific updates through posted signage and KyleRoadBonds.com as each phase progresses.
-
The City's Road Bond Website will share regular updates on construction timelines, traffic impacts, detours, and progress milestones. Residents are encouraged to join the Road Bond Program Newsletter for digital updates to stay informed and prepared throughout each stage of the project.
-
If you have any questions or want to learn more, visit KyleRoadBonds.com/contact or call (512) 200-4963.
For road maintenance requests, contact Kyle 3-1-1 by calling 3-1-1 or visiting Kyle311.com.
In accordance with Title VI of the Civil Rights Act of 1964 and related statutes, it is the policy of the City of Kyle to ensure that no person shall be excluded from participation in, denied the benefits of, or otherwise subjected to discrimination under any programs or activities on the grounds of race, color, national origin, sex, age, or disability.