OLD STAGECOACH ROAD - CENTER STREET

Limits on the 3 segments that will be constructed independently to accelerate delivery:

Old Stagecoach Road North: From Six Creeks Boulevard to Veterans Drive

Old Stagecoach Road: From Center Street to Six Creeks Boulevard

Center Street: From Veterans Drive to Old Stagecoach Road

The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.

Overview

Project Updates

December 2025

Old Stagecoach Road North- Final Design

The project has passed an important design milestone and is moving into the final phase of plan development. The complete, bid-ready construction plans are expected by February 13, 2026. In addition, all initial right-of-way offers have been sent to affected property owners, allowing the City to continue moving forward with land acquisition needs for the project.

Old Stagecoach Road - Final Design

Project design remains at about 90% complete, with the next set of detailed, near-final plans expected by December 23, 2025. City Council has approved the next phase of electrical coordination work, and all right-of-way needed for the project has been secured, allowing the project to continue moving forward without property-related delays.

Center Street (West Segment) - Final Design

Project design is nearly complete, with final, construction-ready plans expected by December 12, 2025. Utility companies are also preparing to begin relocating lines in early December, which is an important step before construction can move forward.

  • Old Stagecoach Road North

    • Length: 0.50 miles

    • Location: Veterans Drive to Six Creeks Boulevard

    Old Stagecoach Road

    • Length: 1.02 miles

    • Location: Six Creeks Boulevard to Center Street

    Center Street (West Segment)

    • Length: 0.62 miles

    • Location: Old Stagecoach Road to Veterans Drive

  • Old Stagecoach Road North

    • Roadway reconstruction and widening improvements

    Old Stagecoach Road

    • Roadway reconstruction and widening improvements

    Center Street (West Segment)

    • Expand the roadway footprint to one lane in each direction and widen center turn lane

  • Construction funded by the City of Kyle’s 2022 Road Bond

    Total Project Cost = $41.2 M

    • Design Phase: Preliminary design is currently in progress

    • Requests for Construction Proposals: Kyle City Council opted to bid this and the Center Street project independently to accelerate delivery, despite some temporary travel delays during construction

    • Construction is anticipated to begin in early 2026, anticipated completion in Fall 2027

Sign Up For Updates

Schedule and Project Status

Project Resources

Previous Project Updates

Old Stagecoach Road Nears Final Design; Kyle Parkway/Lehman Extension Plans Completed

August 20, 2025

The Old Stagecoach Road project has reached 70% of its design phase, aiming to widen the corridor to four lanes and add roundabouts at Six Creeks and Center Street. Meanwhile, the design for the Kyle Parkway/Lehman Road Extension is now fully complete. This 1.3-mile extension will connect Bunton Creek Road to Dacy Lane with four lanes and four roundabouts, marking a major step forward in Kyle’s road improvements.

Progress Update: Bebee PS&E at 85%, Old Stagecoach Design 50% Done, Kyle Parkway Designs Due July 21

July 17, 2025

The City of Kyle is making steady progress on several road projects. Bebee Road East is 85% designed and will include three roundabouts to improve traffic flow. Old Stagecoach Road is halfway through design and will expand to four lanes with roundabouts at Six Creeks and Center Street. Final designs for the Kyle Parkway and Lehman Road Extension are expected by July 21, adding more connectivity and roundabouts to the area.

Get Your Questions Answered Virtually or In-Person at the 2022 Road Bond Open House

March 30, 2025

The City of Kyle is hosting a Road Bond Program Open House on Thursday, April 10 at City Hall (100 W. Center Street) beginning at 5:30 p.m. Residents can learn about eight road improvement projects approved in the 2022 bond, review project timelines and designs, ask questions of officials, and share feedback. There will be both a live-stream panel and in-person stations so everyone can participate.