OLD STAGECOACH ROAD - CENTER STREET
Limits on the 3 segments that will be constructed independently to accelerate delivery:
Old Stagecoach Road North: From Six Creeks Boulevard to Veterans Drive
Old Stagecoach Road: From Center Street to Six Creeks Boulevard
Center Street: From Veterans Drive to Old Stagecoach Road
The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.
Overview
Project Updates
December 2025
Old Stagecoach Road North- Final Design
The project has passed an important design milestone and is moving into the final phase of plan development. The complete, bid-ready construction plans are expected by February 13, 2026. In addition, all initial right-of-way offers have been sent to affected property owners, allowing the City to continue moving forward with land acquisition needs for the project.
Old Stagecoach Road - Final Design
Project design remains at about 90% complete, with the next set of detailed, near-final plans expected by December 23, 2025. City Council has approved the next phase of electrical coordination work, and all right-of-way needed for the project has been secured, allowing the project to continue moving forward without property-related delays.
Center Street (West Segment) - Final Design
Project design is nearly complete, with final, construction-ready plans expected by December 12, 2025. Utility companies are also preparing to begin relocating lines in early December, which is an important step before construction can move forward.
-
Old Stagecoach Road North
Length: 0.50 miles
Location: Veterans Drive to Six Creeks Boulevard
Old Stagecoach Road
Length: 1.02 miles
Location: Six Creeks Boulevard to Center Street
Center Street (West Segment)
Length: 0.62 miles
Location: Old Stagecoach Road to Veterans Drive
-
Old Stagecoach Road North
Roadway reconstruction and widening improvements
Old Stagecoach Road
Roadway reconstruction and widening improvements
Center Street (West Segment)
Expand the roadway footprint to one lane in each direction and widen center turn lane
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $41.2 M
-
Design Phase: Preliminary design is currently in progress
Requests for Construction Proposals: Kyle City Council opted to bid this and the Center Street project independently to accelerate delivery, despite some temporary travel delays during construction
Construction is anticipated to begin in early 2026, anticipated completion in Fall 2027
Schedule and Project Status
Project Resources
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Looking for detailed information about the Old Stagecoach Heritage Live Oak?
Visit our dedicated Old Stagecoach Heritage Live Oak Tree page.
Previous Project Updates
Old Stagecoach Road Nears Final Design; Kyle Parkway/Lehman Extension Plans Completed
August 20, 2025
The Old Stagecoach Road project has reached 70% of its design phase, aiming to widen the corridor to four lanes and add roundabouts at Six Creeks and Center Street. Meanwhile, the design for the Kyle Parkway/Lehman Road Extension is now fully complete. This 1.3-mile extension will connect Bunton Creek Road to Dacy Lane with four lanes and four roundabouts, marking a major step forward in Kyle’s road improvements.
Progress Update: Bebee PS&E at 85%, Old Stagecoach Design 50% Done, Kyle Parkway Designs Due July 21
July 17, 2025
The City of Kyle is making steady progress on several road projects. Bebee Road East is 85% designed and will include three roundabouts to improve traffic flow. Old Stagecoach Road is halfway through design and will expand to four lanes with roundabouts at Six Creeks and Center Street. Final designs for the Kyle Parkway and Lehman Road Extension are expected by July 21, adding more connectivity and roundabouts to the area.
Get Your Questions Answered Virtually or In-Person at the 2022 Road Bond Open House
March 30, 2025
The City of Kyle is hosting a Road Bond Program Open House on Thursday, April 10 at City Hall (100 W. Center Street) beginning at 5:30 p.m. Residents can learn about eight road improvement projects approved in the 2022 bond, review project timelines and designs, ask questions of officials, and share feedback. There will be both a live-stream panel and in-person stations so everyone can participate.