OLD STAGECOACH ROAD - CENTER STREET

Limits on the 3 segments that will be constructed independently to accelerate delivery:

Old Stagecoach Road North: From Six Creeks Boulevard to Veterans Drive, with a new roundabout constructed at the Six Creeks Boulevard intersection.

Old Stagecoach Road: From Center Street to Six Creeks Boulevard

Center Street: From Veterans Drive to Old Stagecoach Road, with a new roundabout constructed at the Old Stagecoach Road intersection.

Project Updates

Summer 2026

Old Stagecoach Road - Final Design

The final design plans (100% PS&E) have been submitted. All necessary right-of-way for the roadway improvements have been secured, and utility relocation work is scheduled to begin this Summer to prepare the area for construction.

Center Street (Off TxDOT System) - Contractor Coordination

The project is advancing toward construction following City Council approval of contractor selection in April. Utility relocation is expected to begin this Summer.

Old Stagecoach Road North - Final Design

The final design plans (100% PS&E) were submitted this Spring. In addition, all right-of-way is expected to be complete by this Summer.

Overview

The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.

  • Old Stagecoach Road North

    • Length: 0.50 miles

    • Location: Six Creeks Boulevard to Veterans Drive (RM 150)

    Old Stagecoach Road

    • Length: 1.02 miles

    • Location: Center Street to Six Creeks Boulevard

    Center Street (West Segment)

    • Length: 0.62 miles

    • Location: Old Stagecoach Road to Veterans Drive (RM 150)

  • Old Stagecoach Road North

    • 4-lane reconstruction and widening

    Old Stagecoach Road

    • Expand roadway to one lane in each direction with a middle left turn lane

    Center Street (West Segment)

    • Expand roadway to one lane in each direction with a middle left turn lane

  • Construction funded by the City of Kyle’s 2022 Road Bond

    Total Project Cost = $41.2 M

  • Kyle City Council opted to bid all three segments independently to accelerate delivery.

    Old Stagecoach Road North

    • Construction: Spring 2026 - Summer 2027

    Old Stagecoach Road

    • Construction: Spring 2026 - Summer 2027

    Center Street (West Segment)

    • Construction: Spring 2026 - Summer 2027

Schedule and Project Status

Project Resources

Navigating Construction Near Your Home or Business

Review our Construction Survival Guide for how to stay up-to-date and informed.

Previous Project Updates

Old Stagecoach Road Nears Final Design; Kyle Parkway/Lehman Extension Plans Completed

August 20, 2025

The Old Stagecoach Road project has reached 70% of its design phase, aiming to widen the corridor to four lanes and add roundabouts at Six Creeks and Center Street. Meanwhile, the design for the Kyle Parkway/Lehman Road Extension is now fully complete. This 1.3-mile extension will connect Bunton Creek Road to Dacy Lane with four lanes and four roundabouts, marking a major step forward in Kyle’s road improvements.

Progress Update: Bebee PS&E at 85%, Old Stagecoach Design 50% Done, Kyle Parkway Designs Due July 21

July 17, 2025

The City of Kyle is making steady progress on several road projects. Bebee Road East is 85% designed and will include three roundabouts to improve traffic flow. Old Stagecoach Road is halfway through design and will expand to four lanes with roundabouts at Six Creeks and Center Street. Final designs for the Kyle Parkway and Lehman Road Extension are expected by July 21, adding more connectivity and roundabouts to the area.

Get Your Questions Answered Virtually or In-Person at the 2022 Road Bond Open House

March 30, 2025

The City of Kyle is hosting a Road Bond Program Open House on Thursday, April 10 at City Hall (100 W. Center Street) beginning at 5:30 p.m. Residents can learn about eight road improvement projects approved in the 2022 bond, review project timelines and designs, ask questions of officials, and share feedback. There will be both a live-stream panel and in-person stations so everyone can participate.