OLD STAGECOACH ROAD - CENTER STREET
Limits on the 3 segments that will be constructed independently to accelerate delivery:
Old Stagecoach Road North: From Six Creeks Boulevard to Veterans Drive, with a new roundabout constructed at the Six Creeks Boulevard intersection.
Old Stagecoach Road: From Center Street to Six Creeks Boulevard
Center Street: From Veterans Drive to Old Stagecoach Road, with a new roundabout constructed at the Old Stagecoach Road intersection.
Project Updates
Summer 2026
Old Stagecoach Road - Final Design
The final design plans (100% PS&E) have been submitted. All necessary right-of-way for the roadway improvements have been secured, and utility relocation work is scheduled to begin this Summer to prepare the area for construction.
Center Street (Off TxDOT System) - Contractor Coordination
The project is advancing toward construction following City Council approval of contractor selection in April. Utility relocation is expected to begin this Summer.
Old Stagecoach Road North - Final Design
The final design plans (100% PS&E) were submitted this Spring. In addition, all right-of-way is expected to be complete by this Summer.
Overview
The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.
-
Old Stagecoach Road North
Length: 0.50 miles
Location: Six Creeks Boulevard to Veterans Drive (RM 150)
Old Stagecoach Road
Length: 1.02 miles
Location: Center Street to Six Creeks Boulevard
Center Street (West Segment)
Length: 0.62 miles
Location: Old Stagecoach Road to Veterans Drive (RM 150)
-
Old Stagecoach Road North
4-lane reconstruction and widening
Old Stagecoach Road
Expand roadway to one lane in each direction with a middle left turn lane
Center Street (West Segment)
Expand roadway to one lane in each direction with a middle left turn lane
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $41.2 M
-
Kyle City Council opted to bid all three segments independently to accelerate delivery.
Old Stagecoach Road North
Construction: Spring 2026 - Summer 2027
Old Stagecoach Road
Construction: Spring 2026 - Summer 2027
Center Street (West Segment)
Construction: Spring 2026 - Summer 2027
Schedule and Project Status
Project Resources
-
Click on the title below to view each segment.
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Looking for detailed information about the Old Stagecoach Heritage Live Oak?
Visit our dedicated Old Stagecoach Heritage Live Oak Tree page.
Previous Project Updates
Old Stagecoach Road Nears Final Design; Kyle Parkway/Lehman Extension Plans Completed
August 20, 2025
The Old Stagecoach Road project has reached 70% of its design phase, aiming to widen the corridor to four lanes and add roundabouts at Six Creeks and Center Street. Meanwhile, the design for the Kyle Parkway/Lehman Road Extension is now fully complete. This 1.3-mile extension will connect Bunton Creek Road to Dacy Lane with four lanes and four roundabouts, marking a major step forward in Kyle’s road improvements.
Progress Update: Bebee PS&E at 85%, Old Stagecoach Design 50% Done, Kyle Parkway Designs Due July 21
July 17, 2025
The City of Kyle is making steady progress on several road projects. Bebee Road East is 85% designed and will include three roundabouts to improve traffic flow. Old Stagecoach Road is halfway through design and will expand to four lanes with roundabouts at Six Creeks and Center Street. Final designs for the Kyle Parkway and Lehman Road Extension are expected by July 21, adding more connectivity and roundabouts to the area.
Get Your Questions Answered Virtually or In-Person at the 2022 Road Bond Open House
March 30, 2025
The City of Kyle is hosting a Road Bond Program Open House on Thursday, April 10 at City Hall (100 W. Center Street) beginning at 5:30 p.m. Residents can learn about eight road improvement projects approved in the 2022 bond, review project timelines and designs, ask questions of officials, and share feedback. There will be both a live-stream panel and in-person stations so everyone can participate.