BEBEE ROAD

West Segment: From IH 35 Northbound Frontage Road to Sunlight Boulevard

East Segment: From Sunlight Boulevard to east of Green Pastures Road

Overview

West segment: Under construction, this project will realign the sharp curves and add capacity to a 1-mile stretch of Bebee Road between northbound frontage road of IH 35 and Sunlight Boulevard with a roundabout at the intersection of the new Kohlers Crossing and Bebee Road.

East segment: Approximately 2.1 miles of a new four-lane minor arterial roadway will be constructed from Sunlight Boulevard to east of Green Pastures Road, along with new roundabouts at the following intersections: Bebee Road & Dacy Lane, Bebee Road & Goforth South, and Bebee Road & Goforth North.

Project Updates

March 2026

Bebee Road (West) – Construction

Construction on Bebee Road (West) continues alongside the Kohlers to Seton project. Crews are actively working along the future Bebee Road connection from the IH-35 northbound frontage road to the planned Bebee Road/Kohlers Crossing roundabout.

Current work includes building up the new roadway, installing storm drainage pipes, and continuing embankment work near the future Vybe Trail. Crews are also excavating the future detention pond, constructing retaining wall foundations, and coordinating and relocating utilities to prepare for the new roadway.

Bebee Road (East) – Final Design

The design plans were submitted and review was complete in January. The team is completing final coordination related project limit revisions before everything is fully finalized.

  • West Segment

    • Length: Approximately 0.7 mile

    • From IH 35 Northbound Frontage Road to Sunlight Boulevard

    East Segment

    • Length: 2.1 miles

    • From Sunlight Boulevard to east of Green Pastures Road

  • West Segment

    • 4-lane minor arterial road

    • Two-lane roundabout at Bebee Road & Kohlers Crossing

    • Addition of a right turn lane at IH 35 Northbound Frontage Road intersection

    East Segment

    • 4-lane minor arterial road

    • Three roundabouts planned at Dacy Lane, South Goforth, & North Goforth

  • Construction funded by the City of Kyle’s 2022 Road Bond

    Total Project Cost = $66.7 M

  • West Segment

    • Construction began in Summer 2025 and is anticipated to be complete in Summer 2027

    East Segment

    • Final Design in progress. Construction to begin Fall 2027 and complete in Fall 2029

On July 17, 2025, the City of Kyle celebrated an exciting milestone — breaking ground on two major road projects from the 2022 Road Bond Program. Work is officially underway on the widening of Bebee Road and the extension of Kohlers Crossing to Seton Parkway, both designed to improve safety, connectivity, and traffic flow for our growing community.

Groundbreaking Event

Schedule and Project Status

Project Resources

Previous Project Updates

Two Voter-Approved Road Bond Projects Underway on East of I-35

July 18, 2025

The City of Kyle recently began construction on two significant road improvement projects, the extension of Kohlers Crossing and the widening of Bebee Road, as part of the 2022 Road Bond Program. These initiatives, with a combined investment of over $130 million, aim to alleviate traffic congestion, improve east-west connectivity, and support the city's rapid growth. Both projects will be completed in multiple segments, with the first phases of construction already underway. The projects were approved by voters in November 2022 and are two of eight planned transportation projects intended to enhance the city's overall transportation network.

Bebee at 85% PS&E, Old Stagecoach design at 50%, and Kyle Parkway designs due 7/21

July 17, 2025

Design is picking up speed! With 85% of PS&E complete, Bebee Road East is getting closer to construction. Three new roundabouts will boost safety and traffic flow at Dacy and both Goforth intersections.

City of Kyle to Break Ground on Two Critical Road Bond Projects East of I-35

July 10, 2025

The City of Kyle is holding a ceremonial groundbreaking on July 17 to mark the start of two major road improvement projects: the extension of Kohlers Crossing and the widening of Bebee Road. Both projects, which are part of the voter-approved 2022 Road Bond Program, are located east of I-35 and are designed to improve traffic flow and connectivity between the east and west sides of the city. The Kohlers Crossing extension will create a direct route to Seton Hospital, while the Bebee Road project will expand the road to four lanes and add a new roundabout at its intersection with Kohlers Crossing to enhance safety and traffic efficiency. These are the second and third projects from the bond to begin construction, following the extension of Marketplace Avenue, which is set to open later this summer.