BEBEE ROAD

West Segment: From IH 35 Northbound Frontage Road to Sunlight Boulevard

East Segment: From Sunlight Boulevard to east of S Goforth Road

Bebee Road Closure

Beginning Wednesday, June 17, and continuing through Saturday, October 31, Bebee Road will be temporarily closed at IH-35 as part of the 2022 Road Bond Program construction project.

During the closure, traffic will be detoured through the new IH-35/Kohlers Crossing intersection and along the Kohlers Crossing extension, reconnecting with Bebee Road west of Republic Drive. One lane in each direction will remain open to accommodate through traffic. 

Access to Lakeside Crossing from Bebee Road will remain open during this phase of construction.

The work being done on Bebee Road includes widening it from two lanes to four with a center turn lane, the addition of drainage, curbs, and sidewalks along both sides.

Motorists may experience delays and are encouraged to use alternate routes when possible. Please follow all posted traffic control devices, watch for construction crews and equipment, and use extra caution when traveling through the work zone.

Project Updates

Summer 2026

Bebee Road (West) – Construction

Construction on Bebee Road (West) continues along the future alignment between Republic Drive and Dacy Lane, with activities focused specifically on roadway development within the Bebee segment. Ongoing work includes roadway embankment construction, stormwater drainage pipe installation, utility coordination, and continued preparation of roadway base and pavement structure.

Upcoming work will focus on roadway improvements between existing Bebee Road and Republic Drive, including base course placement, curb and gutter installation, sidewalk construction, temporary shoefly traffic alignment work, and drainage stabilization using rock riprap. These activities continue advancing the future connection between Bebee Road and the Kohlers corridor.

Bebee Road (East) – Final Design

Design remains at 95% completion. The final design schedule continues to be updated based on the tie-in location change. The previously planned roundabout at Bebee Road and North Goforth Road has been removed from the project scope.

Overview

West segment: Under construction, this project will realign the sharp curves and add capacity to a 1-mile stretch of Bebee Road between northbound frontage road of IH 35 and Sunlight Boulevard with a roundabout at the intersection of the new Kohlers Crossing and Bebee Road.

East segment: Approximately 2 miles of a new four-lane minor arterial roadway will be constructed from Sunlight Boulevard to east of S. Goforth Road, along with new roundabouts at the following intersections: Bebee Road & Dacy Lane, and Bebee Road & South Goforth.

  • West Segment

    • Length: Approximately 0.7 mile

    • From IH 35 Northbound Frontage Road to Sunlight Boulevard

    East Segment

    • Length: 2 miles

    • From Sunlight Boulevard to east of S. Goforth Road

  • West Segment

    • 4-lane minor arterial road

    • Two-lane roundabout at Bebee Road & Kohlers Crossing

    • Addition of a right turn lane at IH 35 Northbound Frontage Road intersection

    East Segment

    • 4-lane minor arterial road

    • Two roundabouts planned at Dacy Lane and South Goforth

  • Construction funded by the City of Kyle’s 2022 Road Bond

    Total Project Cost = $66.7 M

  • West Segment

    • Construction began in Summer 2025 and is anticipated to be complete in Summer 2027

    East Segment

    • Final Design in progress. Construction to begin Fall 2027 and complete in Fall 2029

Road Design Cross Section

Schedule and Project Status

Project Resources

Navigating Construction Near Your Home or Business

Review our Construction Survival Guide for how to stay up-to-date and informed.

Previous Project Updates

Two Voter-Approved Road Bond Projects Underway on East of I-35

July 18, 2025

The City of Kyle recently began construction on two significant road improvement projects, the extension of Kohlers Crossing and the widening of Bebee Road, as part of the 2022 Road Bond Program. These initiatives, with a combined investment of over $130 million, aim to alleviate traffic congestion, improve east-west connectivity, and support the city's rapid growth. Both projects will be completed in multiple segments, with the first phases of construction already underway. The projects were approved by voters in November 2022 and are two of eight planned transportation projects intended to enhance the city's overall transportation network.

Bebee at 85% PS&E, Old Stagecoach design at 50%, and Kyle Parkway designs due 7/21

July 17, 2025

Design is picking up speed! With 85% of PS&E complete, Bebee Road East is getting closer to construction. Three new roundabouts will boost safety and traffic flow at Dacy and both Goforth intersections.

City of Kyle to Break Ground on Two Critical Road Bond Projects East of I-35

July 10, 2025

The City of Kyle is holding a ceremonial groundbreaking on July 17 to mark the start of two major road improvement projects: the extension of Kohlers Crossing and the widening of Bebee Road. Both projects, which are part of the voter-approved 2022 Road Bond Program, are located east of I-35 and are designed to improve traffic flow and connectivity between the east and west sides of the city. The Kohlers Crossing extension will create a direct route to Seton Hospital, while the Bebee Road project will expand the road to four lanes and add a new roundabout at its intersection with Kohlers Crossing to enhance safety and traffic efficiency. These are the second and third projects from the bond to begin construction, following the extension of Marketplace Avenue, which is set to open later this summer.

On July 17, 2025, the City of Kyle celebrated an exciting milestone — breaking ground on two major road projects from the 2022 Road Bond Program. Work is officially underway on the widening of Bebee Road and the extension of Kohlers Crossing to Seton Parkway, both designed to improve safety, connectivity, and traffic flow for our growing community.

Groundbreaking Event