KOHLERS TO SETON

Segment 1: IH 35 northbound frontage road to Seton Parkway (currently under construction)

Segment 2: IH 35 improvements that are part of the Texas Department of Transportation (TxDOT) system

Overview

This project will extend Kohlers Crossing to connect with Seton Parkway, creating a new five lane underpass beneath I-35. The new roadway segment will continue as Kohlers Crossing. The work will be completed in two segments:

Main segment (under construction): Extends the road from IH 35 northbound frontage road to Seton Parkway.

IH 35 Improvements (on TxDOT system): Construction of an overpass to create space for the new Kohlers Crossing connection.

December 2025

Kohlers to Seton - Construction

The project’s baseline construction schedule, which outlines the overall plan and timeline for construction, was approved on November 17, 2025. The contractor is now working on an updated, more detailed schedule to guide the next phases of work. All right-of-way and easements needed for the project have been secured, allowing construction to continue without delays related to property access. Current work includes utility installation along the future northbound right-turn lane from IH 35 to Kohlers Crossing and wastewater system improvements at the future Kohlers Crossing intersection.

Kohlers to Seton (IH 35 at Kohlers Crossing)- Early-Stage Design

The design for this project remains at 90% completion. TxDOT has requested a new Independent Cost Estimate, which is expected on December 15, 2025. Once the report is received and TxDOT provides further direction, the team will finalize and submit the 100% schematic design. 

Project Updates

  • Kohlers Crossing to Seton Parkway

    • Length: 1.07 miles

    • Location: Kohlers Crossing at IH 35 Northbound Frontage Rd to Seton Parkway

    IH 35 Overpass at Kohlers Crossing

    • Length: 0.13

    • Location: IH 35 Southbound Frontage Rd to IH 35 Northbound Frontage Rd

    • Widening of existing roadway to a five-lane underpass at IH 35

    • Roundabout at the intersection of the new Kohlers extension and Bebee Road

    • Extending Kohlers Crossing across IH 35, creating a direct route to Seton Hospital

  • Construction funded by the City of Kyle’s 2022 Road Bond

    Total Project Cost = $66.1 M

  • Kohlers Crossing to Seton Parkway

    • Construction began in Summer 2025 and is expected to be completed by Summer 2027

    IH 35 Overpass at Kohlers Crossing

    • Construction is anticipated to begin in Fall 2027 and be completed by Fall 2029

Sign Up For Updates

Groundbreaking Event

On July 17, 2025 the City of Kyle celebrated an exciting milestone — breaking ground on two major road projects from the 2022 Road Bond Program. Work is officially underway on the widening of Bebee Road and the extension of Kohlers Crossing to Seton Parkway, both designed to improve safety, connectivity, and traffic flow for our growing community.

Schedule and Project Status

Project Resources

Previous Project Updates

Two Voter-Approved Road Bond Projects Underway on East of I-35

July 18, 2025

The City of Kyle has broken ground on two major 2022 Road Bond projects east of I-35: the Kohlers Crossing to Seton Parkway extension and the Bebee Road widening. Together totaling over $132 million, these projects will expand road capacity, improve traffic flow, and enhance east-west connectivity to support the city’s rapid growth. They mark the second and third bond projects to begin construction, following Marketplace Avenue earlier this year.

City of Kyle to Break Ground on Two Critical Road Bond Projects East of I-35

July 10, 2025

The City of Kyle will officially break ground on two key roadway projects east of I-35—the extension of Kohlers Crossing to Seton Parkway and the widening of Bebee Road. A groundbreaking ceremony is scheduled for Thursday, July 17 at 9:30 a.m. at 246 Republic Drive. Funded through the voter-approved 2022 Road Bond Program, these projects aim to enhance east-west connectivity, improve traffic flow, and provide better access to Seton Hospital. They represent the second and third projects to begin construction under the bond program, following the Marketplace Avenue extension.

Pre-construction for Bebee and Kohlers to Seton

July 10, 2025

Pre-construction meetings were held on July 9 for both projects, bringing us one step closer to breaking ground. Construction officially kicks off on July 17, with improvements that include wider roadways, turn lanes, and a new roundabout at Bebee Road and Kohlers Crossing to keep traffic moving safely and smoothly.