Committed to supporting safer, more connected roadways in Kyle.

In November 2022, Kyle voters approved Proposition A — a $294 million investment in our city’s future. These funds are helping us create safer streets, reduce congestion, and make it easier for everyone to get around.

The City of Kyle is kicking off 8 major roadway projects across Kyle, adding 10.3 miles of new and improved roads.

These upgrades will:

  • Make travel smoother and safer for drivers, bikers, and pedestrians

  • Strengthen connections between Kyle’s east and west sides

  • Expand the Vybe Trail System to give our community more ways to stay active and connected

OUR PROJECTS

  • BEBEE ROAD

    WEST SEGMENT: CONSTRUCTION SUMMER 2025 - SUMMER 2027

    EAST SEGMENT: CONSTRUCTION FALL 2027- FALL 2029

  • BUNTON CREEK ROAD

    BID ADVERTISEMENT WINTER 2025

    CONSTRUCTION SUMMER 2026 - SUMMER 2028

  • CENTER STREET

    FINAL DESIGN

    CONSTRUCTION FALL 2026 - FALL 2027

  • KOHLERS TO SETON

    IH-35 UNDERPASS: EARLY DESIGN. CONSTRUCTION FALL 2027 - FALL 2029

    TO SETON: CONSTRUCTION SUMMER 2025 - SUMMER 2027

  • KYLE PARKWAY - LEHMAN EXT.

    FINAL DESIGN

    CONSTRUCTION SPRING 2026 - FALL 2027

  • MARKETPLACE AVENUE

    CONSTRUCTION

    COMPLETED SUMMER 2025

  • OLD STAGECOACH ROAD

    OSC NORTH: CONSTRUCTION SPRING 2026 - SUMMER 2027

    OSC: CONSTRUCTION SPRING 2026 - SUMMER 2027

    CENTER STREET (WEST): BID ADVERTISEMENT WINTER 2025. CONSTRUCTION SPRING 2026 - SUMMER 2027

  • WINDY HILL ROAD

    BID ADVERTISEMENT WINTER 2025

    CONSTRUCTION SPRING 2026 - SUMMER 2027